RT 208 & Maple Avenue NJDOT Construction
As of September 10th:
(Trenton) – Route 208 is scheduled to have left lane closures in both directions Friday night to shift traffic as the CR 507/Maple Avenue Bridge over Route 208 replacement project advances in Glen Rock and Fair Lawn, Bergen County. Beginning at 9 p.m. tomorrow, Friday, September 11 until 6 a.m. Saturday, September 12, the left lanes on Route 208 in both directions are scheduled to be closed. The closures and traffic shifts are necessary to install construction barrier and restripe the roadway. Motorists are advised to slow down, use caution and expect delays when traveling through the work zone.
By 6 a.m. Saturday, September 12, all lanes will be restored with traffic on Route 208 in both directions shifted to the right, using the shoulder and/or the acceleration/deceleration lanes as a travel lane. The ramp from CR 507/Maple Avenue northbound to Route 208 northbound and the ramp from Elm Avenue to Route 208 southbound will have stop signs to allow traffic to safely enter the highway. This pattern is expected to remain in place through the end of 2026. The traffic shift is necessary for bridge pier work in the Route 208 median.
As of September 8th:
(Trenton) – Route 208 is scheduled to have daytime lane closures in both directions this week as the CR 507/Maple Avenue Bridge over Route 208 replacement project advances in Glen Rock and Fair Lawn, Bergen County. In addition, CR 507/Maple Avenue is scheduled to have alternating traffic during the day this week.
From 10 a.m. to 2 p.m. Wednesday, September 9 and continuing Thursday, September 10 and Friday, September 11 at the same time, the right lanes on Route 208 in both directions are scheduled to be closed. The closures are necessary for PSE&G to remove overhead wires. At least one lane will be maintained.
In addition, from 9 a.m. to 3 p.m. Wednesday, September 9 and continuing Thursday, September 10 and Friday, September 11 at the same time, CR 507/Maple Avenue is scheduled to have a single lane closure with alternating traffic on the Bridge over Route 208. Motorists are advised to slow down, use caution and expect delays when traveling through the work zone.
This work is part of the $10.4 million federally funded bridge replacement project that will replace the bridge deck and superstructure on the CR 507/Maple Avenue Bridge over Route 208 in Glen Rock and Fair Lawn, Bergen County. In addition, the project will improve bridge under-clearance, drainage, lighting, signage and fencing on the bridge, as well as replace sidewalks and upgrade curb ramps to meet ADA standards. Construction is expected to be completed in fall 2028.
This project supports the Sherrill Administration’s commitment to improving the transportation network by maintaining roads and bridges in a state of good repair to help people and goods move safely and efficiently throughout the state for decades to come.
The precise timing of the work is subject to change due to weather or other factors. Motorists are encouraged to check NJDOT’s traffic information website www.511nj.org for construction updates and real-time travel information and for NJDOT news follow us on X (Twitter) @NewJerseyDOT, on the NJDOT Facebook page, or Instagram @NewJersey.DOT.
If you have any questions, please contact Shivon Harris, Regional Coordinator for NJDOT-Office of Community and Constituent Relations at (609) 963-1982.
Shivon Harris,
Regional Coordinator for NJDOT
Office of Community and Constituent Relations
(609) 963-1982